The heating and cooling system at Frisco's Discovery Center would be rebuilt under a purchase order on the City Council's Dec. 1 consent agenda.
Texas Air Systems would replace the building's 12 existing rooftop units and add four new packaged units, bringing the total on the roof to 16, according to a memo from Administrative Services Director Daniel Ford. The current units date to the building's construction, the memo says, and have needed frequent service calls.
The work also covers changes to the existing ductwork, new equipment sized for how much heating and cooling the interior now needs, and a building automation system for central monitoring, scheduling and control of the equipment. Staff says the changes should make the system more reliable, give it more flexibility by zone and improve energy efficiency.
Cost and timing
The project is estimated at $3,650,000. Staff is asking for a 5% contingency of $182,500, for a total authorization of $3,832,500. The money comes from the Frisco Community Development Corporation's fiscal 2027 budget, and the purchase runs through the city's interlocal agreement with The Interlocal Purchasing System cooperative.
The memo estimates the job will take eight weeks. It does not give a start date or say whether the building will be affected while crews work.
Other building and park work on the agenda
The same consent agenda includes several other maintenance contracts:
- Heritage Museum lighting: $207,561 to Boyd Electric for the second phase of new LED fixtures, completing new fixtures across both of the museum's floors. A first phase last year added a lighting control system and upgraded circuits.
- Athletic fields: $458,196 to Sports Field Solutions to relevel and resod fields 2 and 3 at Northeast Community Park and Field 14 at Harold Bacchus Community Park with hybrid Bermuda turf, plus yearly aeration and top dressing.
- Playgrounds: $200,625 to SofSurfaces for new rubber tile surfacing at the east and west playgrounds at Harold Bacchus Community Park.
- Irrigation controllers: a $570,650 award to Irri-Tech, including contingency, to replace about 90 irrigation controllers in medians and rights of way and add weather-based adjustment of sprinkler run times. Staff calls it part one of a two-part replacement. Irri-Tech was the top-ranked and lowest-cost of the bidders, according to the memo.