Final bill for downtown's 4th Street Plaza adds $1.72 million for alley paving, a sound system and buried power lines

A change order on the Nov. 17 council consent agenda would push the plaza contract to $22.4 million, about 19% over the original bid. Main Street's rebuild also closes out at $20.4 million.

Sofia Marchetti· AI-assisted, edited by Jake Team

November 11, 20262 min read

Civic Plaza Completion - illustration, Jake Team LLC

The contractor that built downtown Frisco's 4th Street Plaza is asking for one last payment of $1.72 million, and the City Council is set to approve it next Tuesday as part of its consent agenda.

Change Order No. 4 with Millis Development and Construction would raise the plaza contract to $22,411,608.66. The council awarded the job in September 2024 for $18,224,956 plus a $500,000 contingency, so the final figure lands about 19% above the original bid, according to a Parks and Recreation memo posted Wednesday with the Nov. 17 agenda.

State law caps change orders at 25% of the original price.

What the money covers

The memo describes the order as a reconciliation of final bid quantities. The largest pieces are:

  • $474,054.83 to pave Boxcar Alley from 3rd to 4th Street
  • $228,450 for a speaker and sound system in the plaza, along Main Street between 3rd and 5th streets, and on Elm and 3rd streets near the parking garage
  • $175,572.80 for tree soil work and a one-year tree service contract
  • $172,209.55 to move overhead franchise utility lines underground
  • $132,947.50 for utility service lines to businesses on Boxcar Alley between 4th and 5th streets
  • $149,504.60 for a city traffic-signal fiber line
  • $357,153.79 in final field adjustments, including changes to building materials, site furniture and drainage

The itemized change order also lists a five-bench timber order, three storm inlets, extra grab bars in the restrooms, and a water line set aside for future businesses.

Where the money comes from

Most of the order, about $1.37 million, would be covered by unspent money already set aside for the plaza and Main Street projects, the memo says. Sources include the Frisco Economic Development Corporation, the Frisco Community Development Corporation, tree mitigation funds and general obligation bonds. The fiber line is part of the city's five-year fiber plan and would be paid for with a bond transfer.

Staff count only the $357,153.79 in field adjustments as a true increase to the downtown budget, to be covered with new bond money.

Main Street closes out too

A second consent item would close the books on the Main Street rebuild from 1st Street to North County Road. Change Order No. 32 with Tiseo Paving Company adds $56,016.29 and brings that contract to $20,372,590.99, a cumulative increase of 6%, according to the Engineering Services memo. The project's overall budget stays the same because the money would be moved within the Main Street account.

The plaza opened in October with a ribbon cutting and a week of concerts. The council meeting starts at 5 p.m. Nov. 17 at City Hall, with the regular session expected to begin around 6:30 p.m.

Sources

agenda.friscotexas.gov

agenda.friscotexas.gov

agenda.friscotexas.gov

Advertisement

Share

Sofia Marchetti· AI-assisted, edited by Jake Team

Sofia Marchetti covers growth, real estate, and new development as Frisco continues to expand.

Related Stories

More in Texas