Legacy Drive would grow to six lanes from Lebanon Road to Stonebrook under a $14.6 million contract Dec. 1

Tiseo Paving's $13.9 million low bid, plus $695,000 for field changes, is on the council's consent agenda. Work would add lanes inside the existing medians on Legacy and Stonebrook from early 2027 into late 2028.

Aiden Calloway· AI-assisted, edited by Jake Team

November 24, 20262 min read

About 1.6 miles of Legacy Drive would get a fifth and sixth lane under a construction contract the City Council takes up Tuesday, Dec. 1.

Tiseo Paving Company, LLC submitted the lowest of seven bids, at $13,905,256, for widening Legacy from Lebanon Road to roughly 1,400 feet north of Stonebrook Parkway, along with a stretch of Stonebrook itself. Staff also wants $695,000 set aside for construction contingencies, bringing the purchase order to $14,600,256.

The item sits on the consent agenda, which the council can approve in a single vote unless members pull it for discussion.

Lanes go inside the medians

According to the engineering department's memo, the new Legacy lanes would be built within the existing median rather than outside the current pavement.

The Stonebrook portion covers about 0.7 miles. Westbound drivers would get a third lane from 4th Army Drive to Legacy, and eastbound drivers a third lane from Edgestone Drive to Legacy, also inside the median. At Teel Parkway and Stonebrook, the plan adds dual left-turn lanes in all four directions.

The contract also covers rebuilding the four bridge approach slabs and abutment backwalls on the Legacy bridge over Stewart Creek, replacing worn roadway panels, signal upgrades, fiber conduit, street lights, pavement markings, storm drain repairs, landscaping and irrigation.

Bids came in under the estimate

Bids were opened Nov. 5 and ranged from Tiseo's figure up to $17,367,684 from Rebcon, LLC. Altus Construction was second at $14,290,725.33. The opinion of probable construction cost had been $18,187,734, the memo says.

Garver, the engineering firm that tabulated the bids, recommended the award in a Nov. 6 letter, citing earlier projects Tiseo completed for the city to its satisfaction. Any use of the contingency money would be documented through change orders negotiated between city staff and the contractor, according to the memo.

Construction is expected to start in the first quarter of 2027 and wrap up in the third quarter of 2028. The project would be paid for with bonds.

The council meeting begins at 5 p.m. at the George A. Purefoy Municipal Center with a closed session, and the public portion is set to resume at about 6:30 p.m.

Sources

agenda.friscotexas.gov

agenda.friscotexas.gov