New street lights for nine corridors, from Rockhill Parkway to Commitment Drive, go to the council in a $1.69 million contract

RCR Telecon's $1.54 million low bid, plus $150,000 for field changes, is on the Dec. 1 consent agenda. Work would start in January and must finish within 270 days.

Marcus Delgado· AI-assisted, edited by Jake Team

November 25, 20262 min read

Frisco street lights - illustration, Jake Team LLC

New street lights would go up along nine existing corridors across the city under a contract on the City Council's Dec. 1 consent agenda.

Staff is asking the council to award the job to RCR Telecon, LLC, the low bidder at $1,535,446.50, and to set aside another $150,000 for construction phase contingencies. That brings the total purchase order to $1,685,446.50, according to a memo from Robert Caskey, the city's capital projects manager for traffic.

The corridors

The memo lists these segments:

  • Wade Boulevard, Preston Road to Ohio Drive
  • Rockhill Parkway, FM 423 to Teel Parkway
  • Frisco Street, Eldorado Parkway to Cobb Hill Drive
  • Internet Boulevard, Warren Parkway to Network Boulevard
  • Gaylord Parkway, Warren Parkway to the Dallas North Tollway
  • Network Boulevard, Internet Boulevard to Gaylord Parkway
  • Lebanon Road, Independence Parkway to SH 121
  • Everwell Lane, PGA Parkway to Commitment Drive
  • Commitment Drive, Dallas Parkway to the BNSF rail line

Fiber and intelligent transportation system conduit would also be laid along Wade, Rockhill and Gaylord as part of the project, the memo says.

The bid tabulation calls for 74 single-arm and 64 dual-arm luminaire poles, each 30 feet tall with 4-foot arms, along with eight new electrical services and about 17,790 linear feet of trenched conduit.

The bids

The city opened eight bids on Nov. 12. They ranged from RCR Telecon's figure to $2,999,000, the memo says. The engineer's estimate on the bid tabulation was $1,817,838.31. According to the memo, RCR Telecon has not worked on any previous Frisco capital improvement projects.

The contingency money would cover field changes or adjustments to quantities, and any use of it would be documented through change orders negotiated between staff and the contractor, the memo says.

Timing and funding

Construction is expected to begin in January 2027, and the contract requires all work to be completed within 270 calendar days. The project would be paid for with bonds. Plans and specifications were prepared by Maldonado-Burkett, L.L.P., according to the draft contract.

Staff recommends approval. Consent items are considered routine and can be acted upon in one motion, according to the agenda.

Sources

agenda.friscotexas.gov

agenda.friscotexas.gov

agenda.friscotexas.gov

agenda.friscotexas.gov

Advertisement

Share

Marcus Delgado· AI-assisted, edited by Jake Team

Marcus Delgado covers Frisco City Hall and municipal politics, following council decisions and how they shape daily life across the city.

Related Stories

More in Texas