Collin College's Health Sciences Center on Wade Boulevard is in its final punch-list stage, with medical equipment going in

A September program report on Friday's trustee agenda says exterior work and landscaping are finished at the three-story building, and crews are working through a statue the city requires.

Hannah Whitfield· AI-assisted, edited by Jake Team

October 27, 20262 min read

Collin College. Photo: Oldag07 (talk) / Wikimedia Commons (CC BY-SA 3.0)

Construction on Collin College's Health Sciences Center in Frisco has moved into its last stretch, according to the monthly program report that the college's trustees receive at their Friday, Oct. 30, meeting.

The report from AECOM, the firm managing the college's 2023 master plan projects, covers work through September. It says exterior finishes and landscaping at the building are complete, and punch-list work, the final round of fixes before a contractor hands over a space, was set to begin the second week of October.

Inside, the construction manager had finished first-floor work except for final finishes in the west lobby, and the second floor was nearing completion. Major medical equipment was being installed, with a target of finishing by early to mid-October, while mechanical, electrical and plumbing systems were being commissioned and balanced.

The report also lists interior signs in fabrication, a security system install and college IT staff wiring the network.

One line notes the team "is working on statue requirement by City of Frisco." The report does not describe the statue.

The college's purchasing staff is preparing to buy the remaining furniture, fixtures and equipment, the report says. Progress photos included in the document show a cath lab, an AR/VR room and student space.

What the building is for

The three-story, 120,000-square-foot center at 9700 Wade Blvd. is a roughly $70 million project, Local Profile reported last December, when the college said it was set to open in January 2027. Radiology, imaging and sonography programs are planned for the first floor and nursing and physical therapy for the second, with the third floor left as a shell for future programs, according to that report.

PBK Architects designed it, McCarthy Building Companies is the builder and AECOM is the owner's representative.

The wider building program

The Frisco building is one of five projects AECOM manages in a program budgeted at about $240.3 million. As of the September report, the college had committed about $206.7 million of that in contracts and spent about $150.5 million. The report lists no items of close attention.

Trustees meet Friday morning at the college's CHEC building on Spur 399 in McKinney. Their 9:15 a.m. work session also covers enrollment and a billboard campaign.

Sources

meetings.boardbook.org

meetings.boardbook.org

localprofile.com

Advertisement

Share

Hannah Whitfield· AI-assisted, edited by Jake Team

Hannah Whitfield covers Frisco ISD, school board meetings, and education news for local families.

Related Stories

More in Texas